|
Carriageway Drainage
In
order to intercept rain water away from the final road
surface, a system of pipes and chambers is installed
beneath the carriageway margins. The pipes usually
range from 150mm plastic poly pipes to 900mm pre-cast
concrete pipes. Carriageway drainage is an important
feature of a road because of the need to channel water
away from the traffic flow as quickly and efficiently
as possible.
Before any drainage works takes
place data sheets are prepared by the site engineers
and located at the position of each chamber providing
the information required to implement the design.
Excavation
of the main drainage trench is generally carried out
by a 20 tonne, 360º tracked excavator with either a
½ or 1 tonne bucket attachment. As each
3 metre section of trench is dug, a support box is lowered
into the sides of the trench. This is particularly
important in wet ground conditions and provides a stable
working area for the site team. Once the box is
in place, the excavation of the trench can be completed
inside the support until the required depth is reached. The
bottom of the trench is lined with an average of 110mm
layer of single size gravel which forms the bedding
for the pipes.
The
next stage involves lowering the pipe sections into
place and joining them by pushing together the male
and female end joints. A gasket around
the pipe end seals the joint. At intervals of between
75 to 100 meters the trench is widened to accommodate
concrete manhole chambers that will regulate drainage
flow and provide important access for future maintenance. The
pipes are joined to the sump by cutting a hole through
the rings and sealing it with grout to ensure the joint
is watertight and airtight.
Steps are fixed inside the manhole
chamber and are orientated so that an operative emerging
from the manhole will be facing oncoming traffic and
will be able to see and be seen. The trench can
now be backfilled around the chambers and above the
main pipes and the area compacted. A final test
is made to the drainage system by filling the pipes
with air and measuring any drop in pressure over a five
minute period, which should amount to no more than 5%loss
of pressure.
The drainage installation is
now complete and the final carriageway earthworks and
pavement construction can progress.
|